2004
This project continues on schedule for a staff move-in during the 3rd weekend in March.
- Interior painting has been completed.
- T-Bar grid has been hung. The ceiling tiles will be installed this week.
- Carpeting has been installed. See the picture at right.
- Interior windows and doors will be hung this week.
- The Herman Miller components arrive from Michigan at the end of this week. Installation of the workstations will begin immediately.
- The skylights have been installed.
- On the exterior, work on the mansard is progressing. See the picture below.
For more information call 875-8600.